The installation of a new 10” waterline and points of connection to the existing City system is underway as part of the Race Street Improvement Project.
Installation work will continue for the next two (2) weeks. During this time, north and sound bound traffic will be detoured on Race Street between East Lauridsen Boulevard and Park Avenue. The detour will be removed once the waterline installation is complete.
Learn more about the $4.9M grant-funded project to improve the Race Street Corridor.