[ARCHIVED] Traffic Advisory - 16th Street Stormwater Retrofit Project

Work continues on the 16th Street Stormwater Retrofit Project. As part of this project, stormwater upgrades are being installed on 16th Street, at the “C,” D,” and “E” Street intersections. These upgrades will help remove pollutants, including total suspended solids, dissolved copper, dissolved zinc and total phosphorus, from stormwater runoff before connecting into Tumwater Creek.  

What’s been accomplished to date? 

New stormwater infrastructure has been installed. Remaining work includes improving and restoring the roads in the work area. This includes the installation of ADA curb ramps and sidewalk on C Street; new curbs and gutters on C and D Streets; street paving and striping on C, D, and E Streets; and roadside restoration and landscaping.

What’s happening next?

Crews will be working at the intersection of C Street and 16th Street on Monday, January 26, between the hours of 7 a.m. and 5 p.m.

This work will require a partial southbound lane closure of C Street in this area. Additionally, 16th Street will be closed at the C Street intersection (see map). Flaggers will be in place to direct traffic around construction. Detour signage will also be installed on 15th and 17th Streets. 

All entrances to Angeles Millwork will be accessible during this time. Normal traffic will resume by 5 p.m.